Back River Gold District - Canada

Following the acquisition of Sabina Gold & Silver in April 2023, B2Gold acquired Sabina’s 100% owned Back River Gold District located in Nunavut, Canada. The Back River Gold District consists of 5 mineral claims blocks along an 80 km belt. Construction is underway at the most advanced project in the district, the Goose Project, and has been de-risked with significant infrastructure in place.

At US$1,600 gold, a March 2021 Updated Feasibility Study on the Goose Project delivers an after-tax NPV5% of C$1.1 billion and an after-tax IRR of 27.7%. At 6 g/t Au, these are the highest grade undeveloped open pits in the world.

B2Gold recognizes that respect and collaboration with the Kitikmeot Inuit Association is central to the license to operate in the Back River Gold District and will continue to prioritize developing the project in a manner that recognizes Inuit priorities, addresses concerns and brings long-term socio-economic benefits to the Kitikmeot Region. B2Gold looks forward to continuing to build on its strong collaboration with the Kitikmeot Inuit Association and Kitikmeot Communities.

As announced in May 2024, development of the open pit and underground was slightly behind schedule due to equipment availability (commissioning and availability of the open pit equipment), adverse weather conditions and the prioritization of critical path construction activities. An additional three months of mining was added to the schedule to ensure that the Umwelt open pit, underground development and crown pillar activities align and that there is significant tailings storage capacity in the Echo open pit. With the schedule change, the mill is expected to start wet commissioning in the second quarter of 2025 with ramp up to full production in the third quarter of 2025. This does not impact the other facets of the project and staffing tables have been adjusted to ensure that capital is conserved. The Company continues to estimate that gold production in calendar year 2025 will be between 120,000 ounces and 150,000 ounces. The updated production profile has resulted in the Company now estimating that average annual gold production for the six year period from 2026 to 2031 will increase to be in excess of 310,000 ounces per year. The Company remains on track to complete an updated Goose Project life of mine plan by the end of the first quarter of 2025.

B2Gold successfully completed the 2024 Winter Ice Road (“WIR”) campaign in the second quarter of 2024 and has delivered all necessary materials from the MLA to complete the construction of the Goose Project. All planned construction year to date in 2024 has been completed and project construction and development continues to progress on track for first gold pour at the Goose Project in the second quarter of 2025 followed by a ramp up to commercial production in the third quarter for 2025. The 2024 sealift was completed successfully on September 30, 2024, with ten ship and one barge having unloaded 123,000 m3 of dry cargo, more than 84 million liters of arctic grade diesel fuel and 58 additional trucks for the 2025 WIR campaign to the MLA from global locations. Sealift offloading performance significantly increased throughout the 2024 sealift due to a newly constructed barge ramp. Current activities at the MLA now include continued maintenance and preparation for the WIR construction and haulage fleet and staging all materials for shipment on the 2025 WIR to the Goose Project site. t

Development of the open pit and underground remain the Company’s primary focus to ensure that adequate material is available for mill startup and that the Echo pit is available for tailings placement. Mining of the Echo pit is meeting production targets and is anticipated to be ready to receive tailings when the mill starts. The underground mine remains on schedule for commencement of production by the end of the second quarter of 2025.

As announced on September 12, 2024, the total Goose Project construction, mine development and sustaining capital cash expenditures estimate (the “Total Goose Project Construction and Mine Development Cost”) before first gold production estimate is C$1,540 million, a C$290 million (or 23%) increase from the previous estimate from January 2024. Approximately 52% (or C$150 million) of the increase can be attributed to the one quarter delay in first gold production previously disclosed, combined with the acceleration of capital items that were previously anticipated to occur after first gold production. The acceleration of certain capital items is expected to make the Goose Project a more reliable and de-risked operation upon mill startup. The accelerated capital items include accelerated purchases of mining equipment versus the previous estimate to ensure continued growth in mining rates through 2025, the building of an accommodation complex at the MLA which will reduce ongoing annual costs associated with running the WIR, the construction of critical infrastructure at the Goose site, inclusive of warehousing, maintenance, mine dry facility, camp facility expansion and the design acceleration of a reverse osmosis plant to optimize water management and lower ongoing operating costs. Approximately 24% (or C$70 million) of the increase in the Construction and Mine Development Costs can be attributed to the increased cost of logistics of shipping materials to the Goose Project site.


Nunavut: Canada's Newest Mining Friendly Territory

On April 1, 1999, the Territory of Nunavut was formed. The groundwork was laid by the signing of the Nunavut Agreement (the “Agreement”) in 1993 between Inuit of the Nunavut Settlement Area and Her Majesty the Queen in right of Canada. As a result of the Agreement, Inuit are the largest landowners in the Territory and a process of environmental assessment and permitting was established. Mineral resource development remains an important economic driver in the Territory. The development of mining projects in the West Kitikmeot region has far reaching impacts, not only for our shareholders but also for the government and residents of the Territory. The Territory has a well established and sophisticated environmental review process allowing all parties to participate in open and transparent review processes. The first project at Back River, the Goose Project, has progressed through this process and is now fully authorized for construction and operations. The development of the Goose Project opens the Back River Gold District for opportunities yet to be discovered.

Additionally, a 20-year renewable land use agreement (Framework Agreement) has been signed with the Kitikmeot Inuit Association which includes an Inuit Impact and Benefit Agreement. Strong support for the Project has been shown by Kitikmeot communities who contribute to the ongoing development of the Project in an environmentally and socially responsible manner.

Supporting documents:

For the latest details and news releases pertaining to the Back River Gold District:

  • Click here for B2Gold’s Q3 2024 Earnings (dated November 6, 2024)
  • Click here for B2Gold’s news release: B2Gold Announces Goose Project Update; Project Construction and Development on Track for First Gold Production in Q2 2025; Total Construction and Mine Development Cash Expenditure Estimate Before First Gold Production Revised to Reflect Current Timeline (dated September 12, 2024)
  • Click here for B2Gold's news release: B2Gold Announces Positive Exploration Drilling Results from its Inaugural Drilling Campaign at the Back River Gold District in Nunavut and Provides an Update on Construction and Mining at the Goose Project (dated November 21, 2023)
  • Click here for B2Gold’s news release: B2Gold Provides Construction Update for the Goose Project in Nunavut, Canada; Construction on Budget and on Track to Pour First Gold in Q1 2025 (dated September 18, 2023)

For a more detailed overview of the Back River Gold District, please refer to the following most recent company documents:

  • Click here for B2Gold’s Q3 2024 Management Discussion & Analysis (“MD&A”) (dated September 30, 2024)
  • Click here for B2Gold’s Q3 2024 Financial Statements (dated September 30, 2024)
  • Click here for B2Gold’s 2024 Annual Information Form (dated March 14, 2024)

Stay Connected

Stay connected with B2Gold by signing up for email updates